1088 Maritime Way Construction

 

The construction for Lepine’s new apartment building at 1088 Maritime Way will require blasting. It is expected to begin the week of October 19 or October 26th and is planned to continue for approximately 3 months. I have been informed that the blasting will occur Monday through Friday, with up to 6 blasts per crew, per day. Residents near the construction site should have received a Notification Letter from Explotech Engineering, the engineering company that is contracted to monitor the blasting vibration.

If you have any concerns or questions, please reach out to Jeff Corace, M-Roc Ltd. Drilling and Blasting at 613-838-4666 or Explotech Engineering at 613-723-2494.

December 2, 2020 Update:

Due to unforeseen circumstances, blasting continues, and it has been re-forecasted to be completed mid-January. You will hear the warning whistles prior to the blasts and then again after.

December 14, 2020 Update:

Blasting operations will cease on December 18th and resume on January 4th. All site operations will cease on December 23rd and will also resume on January 4th. Please reach out should you have any questions or concerns.